|
|
| Backfilling of Section ΒΘ, day 6. Leaflet from the subcontractor’s union calling their members to go out on strike on the 15th of May 2023 ... Eirini Dimitriadou ... Horizontal (normal) ... 15 May 2023 |
| Backfilling of Section ΒΘ, day 4. Unloading sandbags ... Eirini Dimitriadou ... Horizontal (normal) ... 11 May 2023 |
| Backfilling of Section ΒΘ, day 4. Unloading sandbags ... Eirini Dimitriadou ... Horizontal (normal) ... 11 May 2023 |
| Backfilling of Section ΒΘ, day 4. Unloading sandbags ... Eirini Dimitriadou ... Horizontal (normal) ... 11 May 2023 |
| Backfilling of Section ΒΘ, day 4. Unloading sandbags ... Eirini Dimitriadou ... Horizontal (normal) ... 11 May 2023 |
| During backfilling of Section ΒΘ. Unloading sandbags for the retaining wall ... Craig Mauzy ... southeast Horizontal (normal) ... 11 May 2023 |
| During backfilling of Section ΒΘ. Unloading sandbags for the retaining wall ... Craig Mauzy ... southeast Horizontal (normal) ... 11 May 2023 |
| Backfilling of Section ΒΘ, day 5. The backfilling almost completed ... Eirini Dimitriadou ... Horizontal (normal) ... 12 May 2023 |
| Backfilling of Section ΒΘ, day 5. The backfilling almost completed ... Eirini Dimitriadou ... Horizontal (normal) ... 12 May 2023 |
| Backfilling of Section ΒΘ, day 5. The backfilling almost completed. The corner of the Painted Stoa left visible ... Eirini Dimitriadou ... Horizontal (normal) ... 12 May 2023 |
| Backfilling of Section ΒΘ, day 6. Panoramic view of the site; backfilling almost completed. The photo was taken in the morning; work did not continue due to strike announced by the subcontractor's union ... Pia Kvarnström ... north Horizontal (normal) ... 15 May 2023 |
| Backfilling of Section ΒΘ, day 6. View of the site; backfilling almost completed. The photo was taken in the morning; work did not continue due to strike announced by the subcontractor's union ... Pia Kvarnström ... north Horizontal (normal) ... 15 May 2023 |
| Final cleaning of Section ΒΚ to prepare for the geophysic survey. Walls in the northwest corner of section ΒΖ covered with geotextile ... Eirini Dimitriadou ... west Horizontal (normal) ... 18 May 2023 |
| Final cleaning of Section ΒΚ to prepare for the geophysic survey ... Eirini Dimitriadou ... west Horizontal (normal) ... 18 May 2023 |
| Final cleaning of Section ΒΚ to prepare for the geophysic survey. Walls in the northwest corner of section ΒΖ covered with geotextile ... Eirini Dimitriadou ... Horizontal (normal) ... 18 May 2023 |
| Part of the retaining wall in Section ΒΘ collapsed ... Eirini Dimitriadou ... northwest Horizontal (normal) ... 29 May 2023 |
| Part of the retaining wall in Section ΒΘ collapsed ... Eirini Dimitriadou ... north Horizontal (normal) ... 29 May 2023 |
| Part of the retaining wall in Section ΒΘ collapsed ... Eirini Dimitriadou ... northeast Horizontal (normal) ... 29 May 2023 |
| Part of the retaining wall in Section ΒΘ collapsed ... Eirini Dimitriadou ... southeast Horizontal (normal) ... 29 May 2023 |
| Part of the retaining wall in Section ΒΘ collapsed ... Eirini Dimitriadou ... southeast Horizontal (normal) ... 29 May 2023 |
|
|